Hengrong Shitong Anti-UAV Equipment Industry Chain Project Northwest Branch Anti-UAV Project Decoration Engineering Professional Subcontracting Bidding

Budget or price requirementsSee requirement description
Publishing unitSky Information
Requirement typeSeeking Cooperation
DeadlineLong-term valid
Requirement regionNationwide
Publish time2025-12-18 00:43
Browse 2225
Buyer contact detailsSign in to view the phone number; missing details are clearly marked
Sign in to view

Demand Description

Announcement Content

Tenderer Information
Hebei Province Fourth Construction Engineering Co., Ltd. Northwest Branch
Hengrong Shitong AntiDroneEquipment Industry Chain Project
Under Tendering
0
Gao Xiangzhongrui
13073108976
Northwest Branch Anti-UAV Project Decoration Engineering Professional Subcontracting Bidding
Not a qualified supplier of this company, please contact the information publisher

Release time:2025-12-17Deadline:2025-12-19 10:00Bidding Number:lwzb2025-00022
Subcontracting Nature:Professional SubcontractingEngineering Specialty:Decoration EngineeringQuality Target:Provincial High-Quality Project
Pricing Method:Fixed Comprehensive Direct Unit Price MethodApplicable Quota:0.00
Commencement Date:2025-12-24Completion Date:2026-02-02Work period (days):40
On-site survey:Subcontractor to survey independentlyConstruction drawing No.:Bidding documents:See attachment
Material supply:Except for the machinery and materials list provided by the Employer, the Subcontractor is responsible for the rest.Machines and equipment:Except for the machinery and materials list provided by the Employer, the Subcontractor is responsible for the rest.Canteen and dormitory:The Employer does not provide temporary accommodation or a canteen; all food and accommodation are self-arranged.
Water and electricity charges:The Subcontractor shall make its own arrangements.Temporary facilities:The Employer for this project only provides a main water supply connection point and a main power distribution cabinet at fixed locations; primary distribution box (temporary power main distribution cabinet, secondary distribution box; the Subcontractor is responsible for wires, cables below the secondary distribution box, lighting fixtures for temporary lighting, and water pipes, valves, water tanks, etc. from the main water supply connection point to the water use location; the wires, cables, lighting fixtures, etc. used must comply with our company's specification requirementsSubcontract payment:Progress payment: The subcontract contract price is premised on the construction unit paying the project payment to the Employer; within 60 days after the construction unit pays the project payment to the Employer, the Employer shall pay the Subcontractor 70% of the monthly settlement amount. Settlement payment: within 60 days after the project completion settlement and the Subcontractor submits completion materials and proof of full payment of workers' wages (including wage payment details), 95% of the Subcontractor's settlement amount shall be paid. Quality retention money: 5% of the settlement amount shall be the quality retention money, which shall be returned in full without interest if no quality problems occur upon expiration of the defect liability period.
Subcontract scope:Decoration and RenovationAttachment:
  • Anti-UAV Drawings.zip (53MB)
  • Hengrong Shitong Anti-UAV Project Decoration Engineering Professional Subcontract Contract.docx (64KB)
  • Hengrong Shitong Anti-UAV Equipment Industry Chain Project Exterior Wall Decoration Bidding Document.doc (146KB)
Other:
Required qualifications and grade: Decoration Engineering Professional Contracting Grade II or above. The Subcontractor is required to issue a value-added tax special invoice, tax rate 9%.

#Sub-item NameNo.UnitQuantityContentDescriptionRemarks
1Wall waterproofing0114Square meter9,078.37(1) 6-thick DPM20 mortar (1:2.5 cement mortar) compacted and smoothed (2) 5-thick polymer cement waterproof mortar (3) 1.5-thick polymer cement waterproof coating1# Production Plant, 2# Production Plant, 3# Production Plant, 4# Fire Water Tank and Pump Room exterior wall waterproofing
2Exterior wall paint0646m27,578.91(1) Topcoat 1 coat (2) Main coat 1 coat (3) Divide according to design (4) Primer 1 coat (alkali-resistant sealing primer) (5) Apply water-resistant putty1# Production Plant, 2# Production Plant, 3# Production Plant, 4# Fire Water Tank and Pump Room exterior wall real stone paint
3Interior wall surface0670Square meter48,871.69(1) Apply second topcoat (2) Apply first topcoat and primer (3) 3-thick water-resistant putty applied in stages and smoothed1# Production Plant, 2# Production Plant, 3# Production Plant, 4# Fire Water Tank and Pump Room interior wall decoration
I want to bid



Attachment Download


Anti-UAV Drawings.zip Download

Hengrong Shitong Counter-UAV Project Decoration Engineering Professional Subcontract Contract.docx Download

Hengrong Shitong Counter-UAV Equipment Industry Chain Project Exterior Wall Decoration Bidding Document.doc Download

Share
Mobile BrowsingHengrong Shitong Counter-UAV Equipment Industry Chain Project Northwest Branch Counter-UAV Project Decoration Engineering Professional Subcontracting Bidding Mobile Access QR Code
Comments 0

Requirement information shall be subject to the materials provided by the publisher; verify qualifications and terms before trading.Feedback

Buyer contact details

Procuring entitySky Information
Phone number400***8888

Join

Successful enterprise onboarding grants access to multiple privileges

Onboarding hotline: 18307558659

Enterprise Onboarding Access QR Code

Please scan the QR code with your mobile phone to visit

Support

Customer service hotline: 18307558659

Mini Program

Mini Program for more convenient product search

Providing you with professional purchasing agency consulting services

SkyFamily WeChat Mini Program QR Code